On June 21, 2018, FERC found that the Midcontinent Independent System Operator, Inc.’s (“MISO”) Open Access Transmission Tariff (“Tariff”) provisions governing the termination of generator interconnection agreements (“GIAs”) were unjust and unreasonable due to an inconsistency between the terms of the GIA contained in the Tariff and the MISO Generator Interconnection Procedures (“GIP”).  FERC also accepted, after a paper hearing, MISO’s proposed revisions to the GIA and GIP termination provisions, subject to further revisions.  MISO’s Tariff revisions clarified that an interconnection customer could extend its commercial operating date (“COD”) for up to three years without risking termination from MISO, which FERC found, subject to modification, just and reasonable.  Continue Reading FERC Conditionally Approves MISO Tariff Revisions Regarding Termination of GIAs

On June 8, 2018, the U.S. Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) upheld FERC’s re-examination of an order regarding the effective rate for network upgrades in an Interconnection Agreement (“IA”) with the PJM Interconnection, L.L.C. (“PJM”).  A power developer, West Deptford Energy, LLC (“West Deptford”), requested interconnection with PJM.  After the negotiations for the IA commenced, PJM’s effective rate changed, triggering a dispute between the parties as to the appropriate effective rate for the IA: the rate in effect at the start of negotiations or the rate in effect at the time the IA was completed. The D.C. Circuit agreed with FERC’s finding that the governing rate is the rate in effect at the time the IA was completed. Continue Reading D.C. Circuit Upholds FERC’s Decision Regarding the Timing of the Application of an Effective Rate

On June 5, 2018, FERC granted the PJM Interconnection, L.L.C. (“PJM”) independent market monitor’s (“IMM”) request to compel the American Electric Power Services Corporation (“AEP”) to provide certain information related to cost-based offers to the IMM.  The IMM stated in its petition that it needed the information to determine whether AEP’s total costs of variable operations and maintenance (“VOM”) included in its capacity offer raise any market power concerns in the PJM Energy Market.  FERC determined that because the IMM had broad authority under PJM’s Open Access Transmission Tariff (“Tariff”) to request such information, it would grant the IMM’s petition. Continue Reading FERC Approves PJM IMM’s Request for Access to AEP Cost Data for Market Power Analysis

On May 22, 2018, GlidePath Power Solutions LLC (“GlidePath”) filed a complaint with FERC under sections 206 and 306 of the Federal Power Act alleging that PJM Interconnection, L.L.C. (“PJM”) improperly rejected GlidePath’s interconnection request for a proposed battery storage facility (the “Project”).  GlidePath alleged that PJM relied on an impermissible interpretation of its generator interconnection rules, which require demonstration of site control, to unjustly deny interconnection service for the Project, resulting in cancellation of the Project’s interconnection request.  In its complaint, GlidePath requested that FERC find that PJM unjustly, unreasonably, and incorrectly applied its rules regarding site control, and that PJM must restore the queue position held by the Project.  Continue Reading Complaint Asserts PJM Impermissibly Revised Generation Site Control Requirements

On April 19, 2018, FERC issued a final rule (“Order No. 845”) revising its pro forma Large Generator Interconnection Procedures (“LGIP”) and the pro forma Large Generator Interconnection Agreement (“LGIA”) to address reforms of generator interconnection procedures and agreements for generators of more than 20 megawatts.  FERC adopted a majority of the reforms proposed in FERC’s December 15, 2016 Notice of Proposed Rulemaking (“NOPR”). Continue Reading FERC Finalizes Generator Interconnection Procedures and Agreements Reforms

On April 10, 2018, FERC approved the Midcontinent Independent System Operator, Inc.’s (“MISO”) proposed revisions to Attachment X of its Open Access Transmission, Energy and Operating Reserve Markets Tariff (“Tariff”).  Specifically, MISO proposed to require interconnection customers seeking to modify their elected level of Network Resource Interconnection Service (“NRIS”), to do so earlier on in the generator interconnection process. Continue Reading FERC Approves MISO Interconnection Revisions Regarding Modifications to NRIS Designations

On April 2, 2018, FERC denied a complaint alleging that the interconnection process under Midcontinent Independent System Operator, Inc.’s (“MISO”) tariff was unjust and unreasonable because certain wind generators were experiencing delays in the process, such that those customers would not receive a Generator Interconnection Agreement (“GIA”) in time to receive Federal Production Tax Credit (“PTC”) benefits.  In doing so, FERC found that there was no evidence that MISO was not making reasonable efforts to meet interconnection deadlines, as required by its tariff.  FERC added that prior precedent does not require MISO to ensure wind generators receive their GIA in time to receive full PTC benefits. Continue Reading FERC Holds that MISO Interconnection Process Need Not Ensure that Interconnection Customers Receive PTC Benefits

On March 23, 2018, FERC accepted ISO New England Inc.’s (“ISO-NE”) filing to terminate a portion of the Capacity Supply Obligation (“CSO”) for a wind-powered electric generation facility (the “Disputed Portion”) owned by Blue Sky West, LLC (“Blue Sky West”).  Despite protests from Blue Sky West, FERC approved the requested termination, effective March 1, 2018. Continue Reading FERC Accepts ISO-NE Termination of Portion of Capacity Supply Obligation for Wind Generator; Clarifies Timing of ISO-NE Termination Provisions

On March 16, 2018, the U.S. Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) affirmed FERC’s (1) reduction in NorthWestern Corporation’s (“NorthWestern”) Schedule 3 regulation service rate by removing “regulation-down” capacity from the rate’s numerator and increasing the denominator to the full nameplate capacity of NorthWestern’s generating facility and (2) decision to order NorthWestern to refund customers the difference between NorthWestern’s proposed rate and FERC’s approved rate. Continue Reading D.C. Circuit Affirms FERC’s Modifications to NorthWestern’s Regulation Service Rate

On February 21, 2018, FERC accepted PJM Interconnection, L.L.C.’s (“PJM”) Order No. 825 compliance filing, subject to condition.  In Order No. 825, FERC directed each regional transmission organization (“RTO”) and independent system operator (“ISO”) to align settlement and dispatch intervals, and modify certain rules regarding when shortage pricing is triggered. Continue Reading FERC Conditionally Accepts PJM’s Order No. 825 Compliance Filing on Shortage Pricing and Settlement and Dispatch Alignment