On September 16, 2019, FERC accepted revisions to the PJM Interconnection, L.L.C. (“PJM”) tariff that: (1) establish a process by which existing capacity sellers can request removal of their capacity resource’s status; and (2) revise the process for must-offer exceptions due to an existing seller’s physical inability to meet its capacity requirements. The changes clarify how existing capacity resources may, under certain circumstances, effectively elect to “opt out” of PJM’s annual capacity auctions (termed Based Residual Auctions, or “BRAs”).
Continue Reading

On September 19, 2019, FERC proposed substantial revisions to its Public Utility Regulatory Policies Act of 1978 (“PURPA”) regulations.  If adopted, the package of reforms proposed in the Notice of Proposed Rulemaking (“NOPR”) would: (1) allow states more flexibility to incorporate competitive forces when setting avoided cost rates for Qualifying Facilities (“QFs”), (2) modify the “one-mile rule,” (3) reduce the size threshold for the rebuttable presumption about QFs’ ability to access markets, (4) provide clarity on establishing a legally enforceable obligation (“LEO”), and (5) establish a simplified process to challenge a project’s QF status.  FERC requested comments on a number of proposals, which are due 60 days from publication of the NOPR in the Federal Register.
Continue Reading

Summary of NOPR

On September 19, 2019, the Federal Energy Regulatory Commission (FERC) issued a Notice of Proposed Rulemaking (NOPR) proposing to revise its regulations implementing Sections 201 and 210 of the Public Utility Regulatory Policies Act of 1978 (PURPA) in light of changes in the energy industry since 1978.[1]
Continue Reading

On August 30, 2019, FERC instituted a section 206 proceeding to require PJM Interconnection, L.L.C. (“PJM”) to revise its Amended and Restated Operating Agreement (the “PJM Operating Agreement”) in light of a recent reversal from the U.S. Court of Appeals for the District of Columbia Circuit (the “D.C. Circuit”).  In the new section 206 proceeding, FERC is requiring PJM to revise the PJM Operating Agreement to include projects needed solely to address Form No. 715 local planning criteria in PJM’s competitive proposal process, or to show cause why such revisions are not required.  In a concurrent order on remand, FERC also rejected revisions to the PJM Transmission Owner Tariff that had previously been amended to clarify that 100 percent of the costs for projects that are included in the PJM Regional Transmission Expansion Plan (“RTEP”) solely to address individual transmission owner Form No. 715 local planning criteria should be allocated to the transmission owner’s transmission zone.  FERC expects to issue a final order on the section 206 proceeding within 180 days.
Continue Reading

On August 28, 2019, FERC found on voluntary remand from the United States Court of Appeals for the D.C. Circuit (“D.C. Circuit”) that the New York State Department of Environmental Conservation (“New York DEC”) waived its authority under section 401 of the Clean Water Act (“CWA”) to either issue or deny Constitution Pipeline Company, LLC (“Constitution”) a water quality certificate for a proposed 125-mile pipeline project from that would stretch from Pennsylvania to New York (“Project”).  Based on the D.C. Circuit’s decision in Hoopa Valley Tribe v. FERC (“Hoopa Valley”) (see April 24, 2019 edition of the WER), FERC concluded that Constitution’s agreement with the New York DEC to withdraw and resubmit CWA section 401 certification applications did not restart the one-year statutory deadline for the New York DEC to act on Constitution’s application.
Continue Reading

On July 25, 2019, FERC issued an order directing PJM Interconnection, L.L.C. (“PJM”) “not to conduct the 2019 BRA” (Base Residual Auction) in August (“July 2019 Order”).  The 2019 BRA, which will procure capacity for the 2022-2023 Delivery Year, was already delayed from May to August while FERC considered how to apply the PJM Minimum Offer Price Rule (“MOPR”) to resources which receive out-of-market support, including Zero Emissions Credits (“ZECs”) and Renewable Energy Credits (“RECs”).  If the MOPR were applied to units receiving ZECs, RECs, or other out-of-market support, it is expected capacity market prices would be higher in some regions, and market revenues may be lower for some generators receiving ZECs or RECs or their off-takers.
Continue Reading

On July 18, 2019, FERC issued an order denying in part and granting in part a request for clarification or rehearing of Order No. 856, which revised its regulations relating to interlocking officers and directors.  FERC provided additional clarification and explanation, but declined to make any further revisions or to allow rehearing.
Continue Reading

On June 26, 2019, the U.S. District Court of Maine (“District Court”) denied a motion for leave to file an interlocutory appeal to the U.S. Court of Appeals for the First Circuit (“First Circuit”) ultimately concerning whether FERC’s enforcement action against Competitive Energy, LLC and its managing member Richard Silkman (collectively, “Respondents”) was time-barred.  The District Court previously denied two motions for summary judgment, relying on the First Circuit’s decision in United States v. Meyer (“Meyer”), which held that a FERC enforcement action accrues when FERC assesses a penalty, and therefore was not barred.  Respondents argued that the District Court should not have followed the First Circuit’s decision in Meyer because two subsequent United States Supreme Court (“Supreme Court”) decisions—Kokesh v. SEC (“Kokesh”) and Gabelli v. SEC (“Gabelli”)—have overruled Meyer.  In denying the motion for interlocutory appeal, the District Court held that whether Meyer continues to be good law does not present a “controlling question of law as to which there is a substantial ground for difference of opinion.” 
Continue Reading

On March 21, 2019, the Commission issued a proposed order directing two wind energy generators, Cedar Creek Wind Energy, LLC (“Cedar Creek”) and Cedar Creek II, LLC (“Cedar Creek II”) (collectively the “Cedar Creek Entities”) to provide interconnection and transmission service to a proposed wind project, Mountain Breeze Wind, LLC (“Mountain Breeze”) across jointly-owned interconnection customer facilities (“ICIF”) to the Public Service Company of Colorado (“PSCo”) transmission system.  Although Cedar Creek II sought to dismiss the matter as an impermissible attempt by Mountain Breeze to acquire an ownership interest in the ICIF outside of a Federal Power Act (“FPA”) Section 203 or Section 205 proceeding, FERC rejected this characterization and instead found narrowly that Mountain Breeze had properly filed an application for Commission-ordered service under FPA Sections 210 and 211.  FERC directed the parties to attempt to reach an agreement on the terms and conditions for interconnection and transmission service, or a separate order prescribing such terms and conditions would be issued.
Continue Reading

On March 11, 2019, PJM Interconnection, L.L.C. (“PJM”) made a filing informing FERC that it has begun advising Capacity Market Sellers to use both its existing capacity market rules, as well as its proposed Capacity Reform rules while it awaits a final order from FERC on the proposed reforms.  PJM stated that this approach ensures that all Capacity Market Sellers will have satisfied both the existing and PJM’s proposed pre-auction requirements prior to the conduct of the August 2019 Base Residual Auction (for the 2022/2023 Delivery Year) in anticipation of a Commission order.  The Capacity Reform rules include revised Minimum Offer Price (“MOPR”) rules and the “Resource Carve-Out” alternative.
Continue Reading