On February 15, 2017, the PJM Interconnection, L.L.C. (“PJM”) Board authorized more than $1.5 billion in electric transmission projects in the PJM-region as part of the Regional Transmission Enhancement Plan process. According to PJM President and CEO Andy Ott, the current round of project approvals addresses “the growing need to replace aging infrastructure, energy efficiency, and the resulting reduction in the growth of demand for electricity.” Both the list of approved projects and the proposed cost allocation for each project will be the subject of future filings with FERC.

Continue Reading PJM Board Authorizes $1.5 Billion in Transmission Projects

On December 15, 2016, FERC issued a Notice of Proposed Rulemaking (“NOPR”) in which it proposed to revise its regulations and the pro forma Large Generator Interconnection Procedures (“LGIP”) and pro forma Large Generator Interconnection Agreement (“LGIA”). According to FERC, the proposed reforms could help “improve the efficiency of processing interconnection requests for both transmission providers and interconnection customers, maintain reliability, increase energy supply, balance the needs of interconnection customers and transmission owners, and remove barriers to needed resource development.” Comments on the proposed reforms in FERC’s NOPR are due 60 days after publication of the NOPR in the Federal Register. Continue Reading FERC Proposes Generator Interconnection Changes

On December 15, 2016, FERC issued a notice of proposed rulemaking (“NOPR”) that proposed to establish a set of fast-start pricing requirements applicable to regional transmission organizations (“RTO”) and independent system operators (“ISO”). FERC indicated it was issuing the NOPR to address concerns that rates for fast-start resources in RTO and ISO day-ahead and real-time markets do not reflect the value of fast-start resources. Continue Reading FERC Proposes Fast-Start Resource Pricing Rules for RTOs and ISOs

On November 30, 2016, FERC issued an order accepting tariff revisions filed by Public Service Company of Colorado (“PSCo”) regarding penalty charges for energy imbalance and generator imbalance services under Schedules 4 and 9 of PSCo’s open access transmission tariff (“OATT”). FERC found the revisions, which PSCo filed to address the influx of variable wind generation on its system, to provide incentives for accurate scheduling from transmission customers. Continue Reading FERC Approves PSCo Tariff Revisions Regarding Energy and Generator Imbalance Penalty Charges

On November 17, 2016, FERC issued Order No. 831, revising its regulations regarding incremental energy offer caps imposed by Regional Transmission Organizations (“RTOs”) and Independent System Operators (“ISOs”). As a result, RTOs and ISOs will be required to cap each resource’s “incremental energy offer”—the portion of an energy resource’s supply market offer that can vary depending on output or demand levels—at the higher of $1,000/megawatt-hour (“MWh”) or that resource’s verified actual or expected cost-based incremental energy offer. RTOs and ISOs must also cap verified cost-based incremental energy offers at $2,000/MWh when calculating locational marginal prices (“LMP”). According to FERC, Order No. 831 will reduce the likelihood that offer caps will suppress LMPs below the marginal cost of production, as well as ensure fair compensation for generators and more efficient resource dispatching from grid operators. Continue Reading FERC Revises Offer Caps in Regional Wholesale Electricity Markets

On November 4, 2016, FERC issued an order denying a complaint filed by HORUS Central Valley Solar 1, LLC and HORUS Central Valley Solar 2, LLC (jointly, “HORUS”) against the California Independent System Operator Corporation (“CAISO”). In the complaint, HORUS requested that the Commission prevent CAISO from imposing interconnection procedures and study requirements in addition to those already imposed on HORUS by the Western Area Power Administration (“WAPA”). In denying the complaint, FERC reaffirmed its existing policy that generators must obtain transmission service at or beyond the point where facility ownership changes, as well as beyond the interconnection point with the wider integrated grid. Because HORUS sought to connect to WAPA-owned interconnection facilities, and those facilities in turn interconnected with CAISO, HORUS was required to comply with both WAPA’s and CAISO’s interconnection procedures. Continue Reading FERC Upholds Applicability of CAISO Interconnection Procedures for Third-Parties Directly Interconnecting to WAPA-Owned Facilities

On November 8, 2016, FERC approved the California Independent System Operator Corporation’s (“CAISO”) proposed tariff revisions intended to improve the effectiveness of its local market power mitigation procedures by reducing the frequency of instances where such procedures under-predict congestion. Going forward, CAISO will apply mitigation measures at real-time dispatch intervals. Continue Reading FERC Approves CAISO’s Revisions to Local Market Power Mitigation Procedures

On October 31, 2016, FERC approved PJM Interconnection, L.L.C.’s (“PJM”) proposed revisions to Schedule 1 of the PJM Amended and Restated Operating Agreement (“Operating Agreement”) and the parallel provisions of Attachment K-Appendix of the PJM Open Access Transmission Tariff (“Tariff”). The approved revisions modify PJM’s compensation procedures for load reductions during emergency conditions.

Continue Reading FERC Approves Revised Compensation Procedures for PJM Emergency Load Response Program

On October 28, 2016, FERC issued an order that both partially accepted compliance filings and also denied rehearing requests from PJM Interconnection, LLC (“PJM”), Midcontinent Independent System Operator, Inc. (“MISO”) and MISO Transmission Owners regarding Order No. 1000 interregional compliance filings. Of particular concern for the Commission was the parties’ MISO-PJM Joint Operating Agreement (“MISO-PJM JOA”), and whether it failed to satisfy certain required Interregional Cost Allocation Principles. This is the third such order to address the parties’ compliance with the interregional transmission coordination and cost allocation requirements of Order No. 1000. Continue Reading FERC Denies Rehearing of PJM and MISO Order No. 1000 Interregional Compliance Filings

On September 30, 2016, FERC granted a Southwest Power Pool, Inc. (“SPP”) petition for waiver of certain provisions of the SPP Open Access Transmission Tariff (“Tariff”) in order to provide the option of a payment plan to entities affected by SPP’s delayed implementation of a revenue crediting process for transmission upgrades. Continue Reading FERC Grants Second SPP Waiver Request to Permit Payment Plan for Eight-Year Backlog of Transmission Revenue Credits